Saturday, December 31, 2016

New Church Building Construction

Saturday, December 31, 2016
10/19/16 - Another shot of the upper storage room, it's a little cleaner this time.
10/19/16 - Another panorama of the job site. The building shell is more or less finished. Some of the Maranatha Volunteers have left, the rest will be leaving the next day.
10/19/16 - A couple of Maranatha Volunteer vehicles are one the way out and on to the next construction project.
10/19/16 - One or two people remaining then the job site will be empty.
10/19/16 - A view of the right corner of the building. The steeple will be installed the next day.
10/19/16 - A view of the left corner of the building. The steeple will be installed the next day.
10/20/16 - The steeple has been installed.
10/20/16 - The steeple has been installed.
10/20/16 - Another panorama of the site with the new steeple.
10/21/16 - The mostly empty sanctuary.
10/21/16 - The mostly empty sanctuary.
10/21/16 - The right corner of the building. Siding as been started over on the left side.
10/21/16 - Another panorama of the building front. You can see the siding on the left side.
10/24/16 - One section on the front has been finished.
10/24/16 - One section on the front has been finished.
10/25/16 - The front face and the right side have been finished.
10/25/16 - A panorama of the front with siding.
10/25/16 - Working on the siding on the back.
10/25/16 - The baptistry has been put in place and the water and drain hook up has started.
10/26/16 - The baptistry work continues.
10/27/16 - The landing for the future staircase to the second level has been built.
10/27/16 - Another angle of the landing for the future staircase to the second level.
10/27/16 - The guys doing the siding are also covering the underside of the drive through.
10/27/16 - A view of the sanctuary from the AV loft.
10/28/16 - A wide shot of the action going on.
10/31/16 - The new window over the baptistry has finally been installed.
10/31/16 - A closer view of the new window.
10/31/16 - How the window looks from inside the sanctuary.
10/31/16 - The AV loft and sanctuary entrance at the back of the sanctuary with light from the new window shining on them.
11/2/16 - The heating guy has arrived and is starting the install of the heating and air system duct work.
11/2/16 - Installing one of the vents in the ceiling.
11/3/16 - The baptistry plumbing has been installed.
11/3/16 - Larry Gervais and one of our church members, Heyward Jeffcoat, are working on building the platform for the sanctuary.
11/4/16 - A wide shot of the platform base has been finished.
11/7/16 - A closer view of the platform base.
11/7/16 - The new front doors for the church have arrived.
11/8/16 - Work on the installation of the front doors is almost done.
11/8/16 - The new doors from the inside.
11/9/16 - The second level of the platform has been finished.
11/16/16 - A 180° panorama of the side parking area. Crushed gravel is being spread to make a better parking surface.
11/16/16 - Spreading the gravel.
11/16/16 - Spreading the gravel.
11/17/16 - A wide shot from the driveway.
11/17/16 - A 180° panorama of the front right corner of the parking lot.
11/17/16 - More air ducts have been installed in the sanctuary.
11/17/16 - More air ducts have been installed in the sanctuary.
11/22/16 - The Baptistry steps are finished.
12/13/16 - The insulation people are starting their work. You can see it along the ceiling/wall intersection.
12/13/16 - Another view of the insulation.
12/13/16 - Insulation has been put in the ceiling in the upper storage room.

About Aiken Seventh-day Adventist Church

The Aiken Seventh-day Adventist church was founded in the 1950s by a handful of believers who began meeting together in each other’s houses.  Over the last 60+ years our membership has grown and worship facilities have been enlarged.  Construction of our new church building is complete.  We have started holding services at our new building since April 1st 2017!